Lion 800 construction

20 — 21 August
The Assembly of the frames.

 

Usually the process of building the yacht starts with a breakdown field Plaza, that is, tracing the theoretical drawing in full size and Assembly of frames. This is a rather laborious process which takes a very long time. Thanks to cutting parts on a CNC machine, you can skip this part of the work, all items of a set are cut in pure size and in the joints have a locking connection, the parts fit together without a preliminary adjustment.

To date, completed the Assembly and gluing of all the formers, preparing and gluing spent 2 days working alone.

Assembled and glued web frame rings, all the parts removed from the sheets are grouped by purpose, average stack details of the internal rigging, distant stack of parts cladding Lion 800 yachts.

все собранные рамки

Since the component parts when combined do not require adjustment to accelerate the process of impregnating an epoxy adhesive joints, parts can be assembled package.

Tagged

8 thoughts on “Lion 800 construction

  1. looking forward to seeing your successful build : )

    1. Thank you 🙂

  2. Looking good. Have you finished your busy time now ? We may have to apply this technique to my project 🙂

    1. Hi Ray
      A few days I will have time, I do not see any difficulties to use this technology for your project.

  3. Cant wait to see the next update very interesting indeed well done.

  4. Winter photos please 🙂 What do we do now?

  5. Yes, looking forward to seeing more developments.

  6. Thanks to her fine lines, she provides her owners and crew with an exhilarating sailing experience. Be the BELLE of all the classic yacht regattas!