Lion 800 construction

10 – 11 September
Assembly of frames, install the studs for the mounting of internal rigging.
Installation of the frames on the slipway.

Over the past weekend have been completed the Assembly of all frames and installation of studs for fastening of elements of the internal rigging.
Started installing the frames on the slipway, set 5 frames.

Tools and materials

For Assembly use the following materials: frames, rails for support posts of the frames, pine section 50х30 mm screws.
Tools: screwdriver set, hand saw, measuring tool, water level, plumb line, pencil.

The collected frames, is applied to the position of the Diametric plane in accordance with the drawings, the frames are set on the stocks by using the safety stands, position is controlled by means of a plumb plane, and water level.

While working

Layout and installation of curbs and the installation of berth 2 persons 2 days

Tagged

8 thoughts on “Lion 800 construction

  1. looking forward to seeing your successful build : )

    1. Thank you 🙂

  2. Looking good. Have you finished your busy time now ? We may have to apply this technique to my project 🙂

    1. Hi Ray
      A few days I will have time, I do not see any difficulties to use this technology for your project.

  3. Cant wait to see the next update very interesting indeed well done.

  4. Winter photos please 🙂 What do we do now?

  5. Yes, looking forward to seeing more developments.

  6. Thanks to her fine lines, she provides her owners and crew with an exhilarating sailing experience. Be the BELLE of all the classic yacht regattas!

Leave a Reply