Lion 800 construction

In June 2016 year, construction began on a yacht on the draft Lion 800 in this article, we will provide details on the progress of construction, posting photos and video materials, as well as take into account the hours spent on the construction of boats.
And so we begin.

June 3, 2016
Bookmark slipway

Site preparation, concreting of Foundation pile rack.
At this stage, worked 2 Pax, whose main task was to prepare the site for construction, put the slipway and carport.
The preparatory phase and the construction of a slipway took 4 days.

 

IMG_20160813_110426

The slipway is used for assembling frames and cladding parts for this on the surface of the pile stacked sheets of plywood or OSB and get a large enough surface for assembling parts.

August 6, 2016
Kit from CNC kits arrived at the scene.

Tagged

8 thoughts on “Lion 800 construction

  1. looking forward to seeing your successful build : )

    1. Thank you 🙂

  2. Looking good. Have you finished your busy time now ? We may have to apply this technique to my project 🙂

    1. Hi Ray
      A few days I will have time, I do not see any difficulties to use this technology for your project.

  3. Cant wait to see the next update very interesting indeed well done.

  4. Winter photos please 🙂 What do we do now?

  5. Yes, looking forward to seeing more developments.

  6. Thanks to her fine lines, she provides her owners and crew with an exhilarating sailing experience. Be the BELLE of all the classic yacht regattas!

Leave a Reply