In June of 2016 began construction of a yacht project Lion 800 in 2016 basically completed the work on the Assembly of the hull, in the spring of 2017 began the preparatory work for the installation of the cladding.

March 2017
Installing bow and box stringers.

Forsting yachts composite of the Central part cut out of the plywood side pieces made of timber at the side of the stem cut into longitudinal stringers of the boat.
The next step is cutting the stringers, and prepare to install an external covering.

 

 

Tagged , , ,

2 thoughts on “LION 800 CONSTRUCTION PART 2

  1. how many layers of glass will you be doing?

    1. The yacht is covered with two layers of fiberglass with a density of 300 gr.m2